By following a comprehensive maintenance plan tailored to the specific requirements of your kiln and cooler system, you can extend equipment lifespan, optimize performance, and ensure the safety of plant personnel. Regular preventive maintenance is key to minimizing downtime and achieving reliable operation in cement manufacturing.

By focusing on these key areas andimplementing a proactive maintenancestrategy, cement plant operators can ensurethe longevity, reliability, and safety of their kilnoperations. Regular inspections, preventivemaintenance, and adherence to safetyprotocols are essential for minimizingdowntime and optimizing production output incement manufacturing





SHUTDOWN & MAINTENANCE JOBS

AMBUJA CEMENT

.KILN SHUTDOWN JOBS,ALLIGN,REPLACEMENT
.IKN COOLER INTERNAL/REPAIR/REPLAC SD
MAJOR JOBS,RM,RF,DAMPER
Installation of Chain, Rail of DPC.

ULTRATECH CEMENT

BALL MILL SLIDE SHOE REPLACEMENT OUTLET

JK CEMENT

CM2 O/L HEAD,GG PINION,SEPARATOR & SEPEX
Replacement of Cement Mill 2 outlet head with shell , Girth Gear and both pinion and Replacement of Cement Mill 2 internals with new design liners. Including below subjected 02 Jobs :

  • Separator body modification <(>&<)> rotor Replacement with cartage .
  • Sepax Fan Impeller replacement Scope of work .
    Scope of work for outlet head and girth gear with pinion replacement
    • Opening of Mill man holes for Mill unloading
    • Removal of inlet and outlet trunnion bearing top cover
    • Check alignment reading of inlet and outlet trunnion.
    • Dismantling of second chamber shell liners.
    • Dismantling of outlet diaphragm liners and structure.
    • Marking of cut line and reference line on shell
    • Fabrication and erection of shell supporting structure.
    • Erection of spiders inside the shell near cut line
    • Cutting of Mill shell/li>
    • Removal of Girth gear guard
    • Opening of Girth gear joint bolts and flange bolts`
    • Removal of girth gear
    • Removal of both pinion shaft assembly and shifting to work shop
    • Removal of Mill outlet head to trunnion tight fitting bolts
    • Removal of outlet head with shell and shifting to store yard
    • Inspection of outlet trunnion bearing liner and replacement if required.
    • Edge preparation of old shell as per FLS procedure
    • Shifting of new Mill shell with outlet head at position
    • Arrangement to be made for Mill rotation with winch machine
    • Fixing of outlet head with trunnion with loose bolts and pins
    • Boring and reaming of holes in outlet head and trunnion for fixing of tight fitting bolts
    • Fixing and torque tightening of bolts
    • Alignment of new shell with old shell as per FLS procedure
    • Welding of shell joint as per FLS procedure
    • Alignment of Gear box to Main Motor and auxiliary drive


Replacement of Cement Mill 2 internals.

  • Removal of Mill first chamber liners
  • Removal of intermediate diaphragm liners
  • Shifting of intermediate diaphragm by 500 mm towards inlet side
  • 4 Drilling of holes in Mill shell for new location of diaphragm
  • Erection of new V lift liners in first chamber as per AIA procedure
  • Erection of intermediate diaphragm and liners as per AIA procedure
  • Erection of outlet diaphragm structure as per AIA procedure
  • Erection of new classifying liners in Mill second chamber
  • Erection of outlet diaphragm liners
  • Plugging of old holes
  • Torque tightening of all bolts
  • Closing of man holes. CM 2 SEPERATOR REPLACEMENT WITH MODIFIED DESIGN AS STATIC BLADES, ROTOR

CM 2 SEPAX FAN REPLACEMENT ACTIVITIES TO BE CARRIED OUT.

SCOPE OF WORK:
  • NEW IMPELLER SHIFTING AT SITE.
  • ASSEMBLY READINESS.
  • HALF CASING AND DISTANCE PIECE REMOVAL.
  • OLD FAN DISMANTLING AND REMOVAL FROM SITE. TENTAIVE WEIGHT 3 MT.
  • NEW FAN POSITIONING AND FITMENT OF BEARING AND HOUSESING WITH COUPLING.
  • ALINGMENT.
  • HALF CASING AND DISTANCE PIECE FIXING AND BOLT TIGHTINING.
  • NO LOAD AND LOAD TRAIL OF FAN.
  • SHIFTING OF OLD IMPELLER TO DESIRED / MENTIONED LOCATION.
  • REMOVAL OF ALL SCRAP FROM SITE.
  • ALL TOOLS TACKLES WILL BE IN CONTRACTOR SCOPE.
  • IF CRANE RT 20 IS REQUIRED WILL BE PROVIDED BY JKCW TENTAIVE WEIGHT OF FAN IMPELLER ASSEMBLY 3 MT